Agile & Scrum Practice Question 2: Mid Sprint Stakeholder Request

Agile & Scrum · Test 1 · question 2 of 10

Scrum Accountabilitieseasy

Mid-sprint, a senior stakeholder walks up to Priya, one of the Developers, and asks her to "just slip in" a small new feature that is not in the Sprint Backlog. According to the Scrum Guide, how should this request be handled?

Select one answer
Show answer and explanation

Answer:

  • D. The request goes to the Product Owner, who decides whether and where it belongs in the Product Backlog

The Product Owner is accountable for Product Backlog management, including creating and ordering Product Backlog items. The Scrum Guide is direct: "Those wanting to change the Product Backlog can do so by trying to convince the Product Owner." A new feature is new Product Backlog content, so the stakeholder's request goes through the Product Owner, who weighs it against everything else.

- A is wrong: the Sprint Backlog is a plan by and for the Developers, but it is made of Product Backlog items selected in Sprint Planning. Adding a new feature on a stakeholder's word bypasses the Product Owner's ordering, and the Guide says no changes should be made during the Sprint that would endanger the Sprint Goal. - B is wrong: the Scrum Master is not a scope gatekeeper. Their job here would be to help the stakeholder understand how to work with the Product Owner. - C is wrong: invisible side work destroys transparency, one of Scrum's three pillars, and still skips the person accountable for the product's value.

Reference: The 2020 Scrum Guide - Product Owner