Agile & Scrum Practice Question 7: Manifesto Values

Agile & Scrum · Test 1 · question 7 of 10

Agile Manifestoeasy

New market data shows that a feature scheduled for next quarter is now far more valuable than the work in progress. The customer asks to reprioritize, but the project lead refuses: "The plan was approved in January, and we deliver what's in the plan." Which of the four Agile Manifesto values is this response most directly at odds with?

Select one answer
Show answer and explanation

Answer:

  • D. Responding to change over following a plan

The Manifesto for Agile Software Development states four values; the fourth is "Responding to change over following a plan." Holding to the January plan when new information changes what is most valuable is the textbook case. The supporting principle says the same thing: "Welcome changing requirements, even late in development." Note the Manifesto does not call plans worthless: "while there is value in the items on the right, we value the items on the left more."

- A is a real Manifesto value, but the scenario isn't about processes or tools crowding out collaboration between people. - B is a real Manifesto value, but nothing here trades working software for documentation. - C is not one of the four values at all. It sounds plausible, but the four are individuals and interactions, working software, customer collaboration, and responding to change.

References: Manifesto for Agile Software Development; Principles behind the Agile Manifesto