‹ All CI/CD & DevOps Practices questions

CI/CD & DevOps Practices Practice Question 5: DORA Change Fail Rate

CI/CD & DevOps Practices · Test 1 · question 5 of 10

DORA Metricsmedium

At a quarterly review, a team reports: "We made 40 planned production deployments this quarter. 6 of them degraded service and needed immediate intervention, either a rollback or an urgent fix." The team wants to track the figure "6 out of 40" using DORA's software delivery metrics.

Which DORA metric does this figure measure?

Select one answer
Show answer and explanation

Answer:

  • D. Change fail rate

DORA defines change fail rate as the ratio of deployments that require immediate intervention after the deployment. Six of the forty planned deployments needed a rollback or urgent fix, so the change fail rate is 15% (D).

Option A, deployment frequency, counts how many deployments happen in a period (40 this quarter). It does not measure whether those deployments failed.

Option B, failed deployment recovery time, measures how long it takes to recover from a failed deployment. It is a duration, not a ratio. This metric replaced DORA's earlier "time to restore service" (MTTR).

Option C, deployment rework rate, is the ratio of deployments that are unplanned and happen because of a production incident. It counts the urgent fix deployments themselves, not the six planned deployments that caused the trouble. Rework rate is the newer fifth DORA metric; together with change fail rate it makes up DORA's instability measures.

Reference: DORA's software delivery performance metrics (dora.dev)

Practice Test 1 ›

Study guides for CI/CD & DevOps Practices